Schedule

The FRA initiated the NEC FUTURE program in February 2012. During 2012, key tasks included stakeholder and public outreach, data collection and analysis, a scoping process in accordance with National Environmental Policy Act (NEPA) requirements, and development of initial alternatives.

In 2013, principal activities included Preliminary Alternatives development, existing conditions analysis of the NEC FUTURE Study Area, and ongoing public outreach and agency coordination. In 2014, the Preliminary Alternatives were evaluated to determine a smaller set of alternatives for analysis in the Tier 1 Environmental Impact Statement (EIS).

In 2015, the FRA released the Tier 1 Draft EIS for public comment. The Tier 1 Final EIS was released in 2016. The FRA completed the NEPA process with the release of the Record of Decision (ROD) in July 2017. The ROD documents the Selected Alternative for NEC FUTURE. The next step is the completion of a Service Development Plan, which will describe the process for implementing the Selected Alternative.

 

The information posted on this website includes hypertext links or pointers to information created and maintained by other public and/or private organizations. The FRA provides these links and pointers solely for information and convenience. When users select a link to an outside website, they are leaving the NEC FUTURE website and are subject to the privacy and security policies of the owners/sponsors of the outside website. The FRA does not control or guarantee the accuracy, relevance, timeliness or completeness of information contained on a linked website, or endorse the organizations sponsoring linked websites, the views they express, or the products/services they offer. The FRA cannot authorize the use of copyrighted materials contained in linked websites and is not responsible for transmissions users receive from linked websites.